Introduction
We will continue to deliver against our target to be a net zero District by 2050. The Council will deliver this through strong leadership and enabling and will:
As part of the commitment to becoming a net zero Council by 2050, we will meet the following milestones within the next 10 years:
Theme one: Building and assets
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Council |
Implement energy audit of WL operational estate to deliver energy efficient design
Initial focus on operation building surveys will be:
|
Comprehensive understanding of opportunities to retrofit buildings operated & occupied by West Lindsey District Council. Priority areas and timeline for interventions developed Packages of work including specifications for improvements and changes Understanding of energy use patterns across the operational estate & options to change usage and habits. |
Narrative | 2023 to 2030 |
Our Place | Implement new monitoring framework for the Central Lincolnshire Local Plan, including measures for impact of climate change polices. | Measurable impact of the Climate change Policies on development across Central Lincolnshire and West Lindsey. | Narrative, possible target development as plan embeds |
Monitoring Framework 2024/25 Impacts of Policy March 2025 onwards |
Our Place | Delivery of recently announced 3 to 5 year Warm Homes Local Grant scheme. | Improve the energy efficiency of homes across Central and South Lincolnshire Consortium. | 2023 to 2030 | |
Our Council | Bid for PSDF to replace the Guildhall gas heating system. | Improve the energy efficiency & reduce the carbon footprint of the Guildhall. | Narrative & target reduction in CO2 emissions. |
2024 to 2026 |
Our People | Redevelopment of the West Lindsey Leisure Centre to improve energy efficiency of the site. | Improve energy efficiency credentials of the building | Narrative including baseline and projected efficiencies and carbon savings |
2025 to 2026 |
Theme two: Campaigning and lobbying
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Council |
Using the Climate Change Member and Officer working groups continue to engage in active campaigning and lobbying in relation to key priorities for West Lindsey Residents. Considered as a monthly standing agenda item. Implement a targeted lobbying and campaigning strategy. |
The council is actively engaged in emerging issues and opportunities relating to Climate Change. The council proactively influences policy and funding decisions at local, regional, and national levels. Key stakeholders are engaged and supportive of West Lindsey’s climate and sustainability goals West Lindsey’s unique rural perspective is represented in wider policy discussions. |
Number of policy consultations responded to annually (target: at least 5) Number of meetings with regional/national policymakers – including representation at webinars and conferences (target: at least 4 per year) Successful inclusion of West Lindsey’s priorities in regional strategies or funding allocations |
2024 onwards |
Our Place | Engage proactively with the new Mayoral County Combined Authority (MCCA) on environmental and sustainability issues for 2025. |
West Lindsey’s environmental priorities are reflected in MCCA strategies and initiatives. Increased funding and support for local sustainability projects. Improved coordination of county-wide environmental |
Narrative relating to MCCA meetings/consultations participated in. Inclusion of West Lindsey’s priorities in MCCA environmental strategies |
2024 onwards |
Our People | Expand collaborative work with the Lincolnshire Sustainability Officers Group (LSOG) and other key stakeholders. |
Increased knowledge sharing and collaborative working on lobbying and campaigns. Joint funding bids developed and submitted. Unified Lincolnshire voice on key sustainability issues. |
Number of joint initiatives or campaigns launched (target: at least 2 per year). Number of successful joint funding bids (target: at least 1 per year). Narrative report on outcomes of collaboration to Member group. |
2024 onwards |
Theme three: Decision making
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Council | Continued roll out of staff training and broader awareness raising across the council. | Climate change outcomes form core part of decision making across the council. | Narrative | Ongoing |
Our Council | All new and reviewed strategies to include an appropriate approach to mitigating the impacts of Climate Change. |
New strategy delivery action plans will include deliverables against Climate Change priorities. Growth strategy. |
Number of new and reviewed strategies with Climate Change priorities and associated actions. | 2024 onwards |
Our Council | Continue to monitor the impact of the CESIA tool across all decisions and Governance structures in the council. | Demonstrable outcomes of the use of the CESIA tool in decision making for all council business. | Number of decision outcomes impacted as a result of CESIA assessment. | 2024 |
Theme four: Influencing others
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Council | Increased communications output in line with strategy and campaign "small steps, big impact" and publishing a summary achievements document. |
General promotion of activities led by West Lindsey, including grants that are available and how we as a council can support community agendas. | Narrative | 2024 onwards |
Our Council | Increased communications output in line with strategy and campaign "small steps, big impact" and publishing a summary achievements document. |
Increased coverage relating to communications & messaging. |
Number of climate change related articles published. Audience number achieved. |
2024 onwards |
Our People | Continued improvement of the Climate change and sustainability web pages to raise awareness, support our parish councils and community groups to access information. | Community awareness of the opportunities in reducing their carbon footprint and increasing sustainability including the tools to implement change within their area. | Narrative and number of webpage hits annually. | 2024 onwards |
Our People | Actively encourage all new Neighbourhood Plan Groups to include specific policies to deliver the strategic aims of the Sustainability, Climate Change and Environment strategy. |
All new Neighbourhood Plans include policies aimed at supporting the delivery of carbon net zero in 2050 and respond to wider sustainability and climate change issues relevant to their area. | Number of Neighbourhood Plans which include specific policies relating to at least 1 of the 10 Climate Change Strategy Themes. |
Ongoing |
Our Place | Working with community groups to support raising awareness of environment and sustainability actions and opportunities. |
Awareness raising of grant applications opportunities. | Narrative, including number of communities supported and sign posted. | 2024 onwards |
Our People | Support particularly small, medium-sized enterprises (SME) to access funds and expertise for reducing carbon pollution – promote resilience support grants. | A reduction in the carbon footprint of businesses across West Lindsey. |
Number of Businesses receiving support annually, including cases studies and narrative. Continued delivery of KSPF funded business support programmes (and grants) until March 2025 (programme may be extended) |
Ongoing |
Our Place | Mapping exercise to understand pipeline of businesses investment opportunities which deliver objectives relating to Environment & Sustainability objectives. Examples include STEP, Scampton, AgriZone, Waterways Strategy, Gainsborough Masterplan refresh, Agri-Tech Twinning, Eco Settlement, and the circular economy. |
Improved understanding of environmental business operating in West Lindsey. Improved engagement to deliver synergies & circular economy. Improved inwards investment. Create a hub for innovation focused on the environment and sustainability across multisectors. |
Narrative | 2025 onwards |
Develop and implement targeted campaigns on key local environmental issues. |
Increased public awareness and Behavioural changes supporting sustainability goals. Enhanced support for council’s environmental initiatives. |
Number of local campaigns launched (target: at least 3 per year – Waste minimisation, energy efficiency, community energy, flood preparedness already identified. Reach and engagement metrics for campaigns (e.g., social media interactions, event attendance). Survey results showing increased public awareness of environmental issues. |
Ongoing | |
Our Place | Continued support of Lincolnshire Wolds AONB Memorandum of Agreement (MoA) Funding. | Continued support of Lincolnshire Wolds Countryside Service | Narrative | 2024 onwards |
Theme five: Land use
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Place | Continued implementation of bio-diversity net gain as part of development management process, including continued training and monitoring. | Measurable 10% net gain in biodiversity across West Lindsey. | Narrative with the potential to develop measures in relation to net gain in the future, including links to other nature based projects in West Lindsey. | 2024/25 onwards |
Our Place |
Green Space Management. Implement UKSPF: 1.6 Green Space Management and Community Project Development. |
Improve management and operation of West Lindsey District Council owned green spaces (linked to UK Shared Prosperity Fund Green Space Officer). | Narrative | 2024 onwards |
Our Place |
Green Space Management. Implement UKSPF: 1.6 Green Space Management and Community Project Development. |
Adoption of woodland management plans to improve accessibility biodiversity, and overall management. |
Adoption of woodland management plan. Option to measure actions following this. |
2024/25 |
Theme six: Power
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Place |
Use new mapping exercise with DNO to increase Work with other Lincolnshire districts to develop a Local Area Energy Plan (LAEP) to guide the transition to a low carbon energy system. |
Officers and members are better informed and able to provide Comprehensive understanding of local energy needs, resources, and opportunities. Clear roadmap for decarbonisation of the local energy system. Increased resilience and energy security for the community. Identification of potential community energy projects and investment opportunities. |
Narrative, case studies. Progress in completion of the LAEP. Projected carbon emissions reduction from LAEP measures. Number of identified renewable energy and energy efficiency projects. Amount of external funding secured for energy projects. |
Ongoing |
Our Place | Switch parish street lighting to well-designed and well directed LED lights. | Parish streetlights owned by West Lindsey District Council upgraded resulting in a reduction in power and CO2 emissions. | Narrative including % of total lighting upgraded to LED, | Ongoing |
Theme seven: Protecting the vulnerable
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Place | Develop and adopt a Communities Strategy. |
A Communities Strategy will establish the strategic approach to delivering community support, services and intervention to achieve Identify communities at risk, which will include those at risk of impacts due to Climate Change. Strategy will be supported by an Action Plan to oversee delivery of community services and projects. |
Adoption of Communities Strategy and associated action plan. | 2024-2026 |
Our People | Develop resources to support communities vulnerable to the impacts of climate change. |
Better informed communities. Communities develop own local resilience plans. |
Narrative and numbers | 2025 onwards |
Our People | Engage with the new LRF Resilient Communities project designed to provide tailored support to communities at risk. |
Help communities develop a robust resilience plan. Provide training for town and parish councillors. Coordinate forum for parish, district and LRF representative. Develop evidence base and information mapping to support future emergency response. Arrange best practice events and information between parish councils. |
Narrative and numbers | 2025 onwards |
Our People | Implement and delivery LEAD project on behalf of Central and South Lincolnshire consortium. |
Provide advice and support to hard-to-reach cohorts. Increase utilisation of energy improvement measures to hard-to-treat properties. |
Target number of 500 hard-to-reach cohorts across consortium. Installation of energy efficient measures across over 162 homes. |
2023 onwards, as grant regimes become available. |
Theme eight: Resources and finance
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Council | Preparedness for future funding bids. | Additional monies secured to deliver initiatives in line with the CESS strategy. | Number of bids submitted and outcomes. | Ongoing |
Our Council |
Continue to refresh Treasury Management Strategy to ensure the council invests It is anticipated that as ethical and environmental investment becomes more mainstream that a greater choice of investment opportunities will be available. |
To ensure the council best uses its cash resources to ensure security, liquidity, and yield whilst also taking into account ethical, sustainable and governance factors. The council continue to evaluate the market & products available to maximise ethical and environmental investment whilst promoting financial sustainability. |
Narrative which includes a new Treasury Management Strategy which delivers opportunities for green and ethical financing. |
2025 onwards |
Our Council | Develop an employee benefit scheme which includes promotion of active travel, sustainable travel options and opportunities to deliver positive environmental outcomes to the broader district. |
Improved access to active travel and sustainable travel options. Improved environmental outcomes and wellbeing for staff across the district. |
Narrative and take up numbers. | 2025 onwards |
Our Council | To reduce our carbon footprint through use of digital technology. | More sustainable business practices which includes a reduction in the use of resources and in some circumstances a reduction in the organisations carbon footprint. |
Narrative on specific projects identified for 2024, including but not exhaustively:
|
2024-2026 |
Theme nine: Transport and connectivity
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Council | Implement the new de-carbonisation vehicle replacement strategy. | Provision of a pathway to deliver reliable, cost effective and carbon reduced vehicles, plant and associated equipment, at the right time and at the right cost to support the strategic objectives of the council. |
Reduction in CO2e emissions from the fleet. Metrics for reduction to be established as part of the recommendations in the strategy. |
2024 onwards |
Our Place | Improve connectivity and access to broadband across the district. | Improved digital access to support a reduction in travel where services can be accessed digitally. | Narrative which includes the number of communities that have received improved broadband speed. | 2022 to 2028 |
Our Place | Undertake review community Wi-Fi hotspots. | Improved community access to digital services. | Narrative and number of communities receiving WiFi hot spots and or reviews to support technological improvements. | 2022 to 2028 |
Theme ten: Waste
Corporate plan theme | Action | Outcome | Measure | Timeframe |
---|---|---|---|---|
Our Council | Prepare for and implement separate weekly food waste collections. | Compliance with Environment Act 2021 requirements; reduction in residual waste. | Percentage of households with food waste collections; tonnage of food waste collected. | Planning 2024-2025, full implementation by March 2026 following pilot. |
Our Council | Improve recycling quality and quantity by continuing to promote and expand the “Right Thing, Right Bin” campaign. | Reduced contamination in recycling streams; increased recycling rates. | Recycling contamination rates; overall recycling percentage. | Ongoing through 2025 and beyond. |
Our Council | Adapt to Emissions Trading Scheme (ETS) Changes: [Action] Develop strategies to minimize residual waste sent to energy from waste facilities. | Reduced carbon emissions and potential future costs associated with ETS. | Tonnage of residual waste; estimated carbon emissions from waste. | Planning 2024-2025, implementation from 2026 onwards. |
Our Council | Enhance Waste Prevention and Reuse Initiatives: [Action] Develop and implement a comprehensive waste prevention and reuse program. | Reduced overall waste generation; increased reuse of materials. | Total waste per household; participation in reuse schemes. | 2025 to 2026 |
Our Council | Prepare for Extended Producer Responsibility: Develop systems to accurately measure packaging waste for EPR payments. | Maximized financial benefits from EPR scheme; improved data on waste streams. | Accuracy of waste data reporting; EPR payments received. | 2025 to 2026 |
Our Council | Prepare for Deposit Return Scheme (DRS) Impact: [Action] Assess and plan for the impact of DRS on waste collections and recycling rates. | Smooth transition to DRS implementation; maintained recycling performance. | Changes in recycling composition; overall recycling rates. | Planning 2025-2026, adaptation 2026 onwards. |